June Construction Update

It has been a while since we last sent an update, rest assured activity has been at an all time high onsite. We’re very proud to report the team at CREST have reached one of the largest and most exciting project milestones – structural completion and top of out construction!
 
Despite many unforeseen delays this progress is a credit to the team. Their hard work and resilience in overcoming the challenges surrounding site constraints, weather and external service providers is a testament to the property that will be delivered.
 
With the structure now complete the team have already made incredible progress internally and are being thorough in their program expectations, ensuring we meet the early spring completion.

What's happening onsite

  • External brickwork facade underway
  • Ground floor block work for commercial spaces completed
  • Ground floor services are now installed
  • Level 1 services roughed in and wall sheeting completed
  • Windows, doors and glazing has been installed on levels 1 & 2
  • Level 2 framing and sheeting being completed
  • Level 3 framing and insulation almost complete
Apartment cut through
Apartment cut through