February Construction Update

We’ve had a very busy few months since our last update which has seen the team transition into the structural phase of the project. The team recently completed the level one pour, taking a whopping 560 cubic metres of concrete. This marks the largest pour the team will undertake for this project. From Level One it’s expected we’ll complete a structural level every three weeks; with an anticipated topping out the structure in early April. We can then turn our focus towards the internal fit-outs and completion later in the year.

In the coming weeks our site team will pour the Level One slab, taking a whopping 560 cubic metres of concrete. This marks the largest pour the team will undertake for this project. From Level One it’s expected we’ll complete a structural level every three weeks; with an anticipated topping out the structure in early April. We can then turn our focus towards the internal fit-outs and completion later in the year.

What's happening onsite

  • Pouring Level One concrete slab
  • Installation of 86 structural precast panels to Level One
  • Commencement of Level Two formwork
  • Roughing in all Level Two electrical, mechanical and plumbing services
  • Pouring Level Two slab towards the end of the month
  • Structural Top out early April (weather permitting)